Who is responsible for costs related to tests and inspections specified in the Contract Documents?

Prepare for the Architect Registration Examination (ARE) 5.0 Construction and Evaluation Test. Study with flashcards and multiple choice questions, complete with hints and explanations. Ace your exam!

The responsibility for costs related to tests and inspections specified in the Contract Documents typically falls on the Contractor. Throughout the construction process, the Contractor is generally accountable for ensuring that the work meets the specified quality and performance standards defined in the Contract Documents. This includes performing or arranging for necessary tests and inspections to verify compliance.

When the Contract Documents specify certain tests, it is understood that the costs associated with these tests and inspections are part of the Contractor's obligations. This allows for the assurance that the work is completed according to the required standards and specifications. The role of the Contractor is to manage these testing and inspection processes, which includes any costs incurred.

The Owner may have responsibilities related to oversight and ensuring that the project is completed satisfactorily, but the financial responsibility for tests and inspections primarily rests with the Contractor as part of their scope of work. This delineation of responsibilities helps maintain clarity in the contract and fosters accountability throughout the construction phase.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy