Which of the following is not included in the Contract Documents?

Prepare for the Architect Registration Examination (ARE) 5.0 Construction and Evaluation Test. Study with flashcards and multiple choice questions, complete with hints and explanations. Ace your exam!

The reason why the bidding instructions are not included in the Contract Documents is that the Contract Documents primarily consist of all the elements that define the terms and conditions for the execution of the work once a contract has been formed. Typically, the Contract Documents include the General Conditions of the Contract, drawings, specifications, and modifications that pertain to the contract after it is signed.

Bidding instructions, on the other hand, are part of the procurement process and serve to guide potential bidders on how to submit their proposals and what information is required for consideration. These instructions precede the contract formation and do not govern the execution of the work subsequently defined in the Contract Documents.

Understanding the structure of the Contract Documents is crucial for architects as it helps clarify what is included during the construction phase and what governs interactions between the owner and contractor after the contract is executed.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy