Which of the following is NOT a requirement for the Contractor before the execution of the Contract?

Prepare for the Architect Registration Examination (ARE) 5.0 Construction and Evaluation Test. Study with flashcards and multiple choice questions, complete with hints and explanations. Ace your exam!

The correct choice indicates that obtaining a building permit is not typically a requirement for the contractor before executing the contract. Instead, it is usually the responsibility of the owner or client to secure the necessary permits and approvals needed to commence construction.

The requirement for the contractor to visit the project site is crucial because it allows them to assess site conditions firsthand, which can influence their pricing and scheduling. Familiarity with the contract documents is essential for the contractor to understand the scope of work, responsibilities, and specifications prior to beginning the project. Executing a representation of actions taken often involves documenting actions or decisions made during the pre-construction phase, which can help ensure accountability and clarity for all parties involved.

In contrast, the responsibility of obtaining the building permit typically falls on the owner, as they are the ones seeking authorization for construction from local authorities. It is important for contractors to understand this distinction, as it clarifies the different roles and responsibilities within a construction project.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy