What is the maximum time allowed to file a suit to enforce a lien after recording it?

Prepare for the Architect Registration Examination (ARE) 5.0 Construction and Evaluation Test. Study with flashcards and multiple choice questions, complete with hints and explanations. Ace your exam!

The maximum time allowed to file a suit to enforce a lien after it has been recorded is indeed 90 days. This timeframe is established to ensure that disputes related to liens are resolved in a timely manner, providing protection to property owners as well as contractors and subcontractors who may have an interest in the property due to unpaid work or materials supplied.

After the 90-day window, the lien may become unenforceable, and those holding the lien lose their rights to take legal action to collect their due payment through the property. Essentially, this stipulation facilitates the prompt resolution of financial disputes in construction and ensures the orderly progression of construction projects.

This specific duration may vary by jurisdiction, but in many places, a 90-day period is standard. Familiarity with local laws, including specific statutes that govern lien enforcement, is essential for professionals in the field.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy