What happens upon the Owner's written notice of termination?

Prepare for the Architect Registration Examination (ARE) 5.0 Construction and Evaluation Test. Study with flashcards and multiple choice questions, complete with hints and explanations. Ace your exam!

Upon the Owner's written notice of termination, the Contractor is required to stop operations and take necessary measures to protect the work that has already been completed. This means that the Contractor must secure the site and preserve the integrity of the work to prevent any further damage or deterioration. This step is essential to ensure that the project can be assessed accurately and safely, whether it's going to be completed by another contractor or if other arrangements are made.

Stopping operations immediately helps mitigate any potential liability or further costs incurred by continuing work that may not be honored due to the termination. Protecting the work also includes ensuring that materials, equipment, and labor are appropriately managed, maintaining safety on the site and safeguarding completed tasks for any potential future use. This reflects standard industry practices in response to termination notices and is critical for the orderly wind-down of the project.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy