What document allocates the entire Contract Sum to various portions of Work?

Prepare for the Architect Registration Examination (ARE) 5.0 Construction and Evaluation Test. Study with flashcards and multiple choice questions, complete with hints and explanations. Ace your exam!

The correct answer focuses on the Schedule of Values, which is a crucial document in construction management that allocates the entire Contract Sum to various portions of Work. This document provides a detailed breakdown of the contract amount into separate line items that correspond to different phases or components of the project. It serves as a financial roadmap for tracking progress and for interim payments, allowing the owner and architect to see how costs are distributed throughout the different aspects of construction.

The Schedule of Values typically reflects the scope of work specified in the contract documents, ensuring that all contractors are aware of how funds are being allocated and what represents progress on the project. This transparency helps manage expectations regarding financial performance and project delivery.

In contrast, the Bid Form is primarily used for submitting a proposal and does not allocate the Contract Sum after the contract is awarded. The Contract Sum Statement is a record of the total contract price but does not individually break down the portions of work. The Work Breakdown Structure is more about organizing tasks and deliverables rather than explicitly allocating finances to various parts of a project.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy