What are some typical documents the Architect is responsible for during Contract Administration?

Prepare for the Architect Registration Examination (ARE) 5.0 Construction and Evaluation Test. Study with flashcards and multiple choice questions, complete with hints and explanations. Ace your exam!

During Contract Administration, the Architect plays a crucial role in the management and coordination of the project's contractual aspects. Documents such as Proposal Requests, Change Orders, and Certificates of Payment are fundamental to this process.

Proposal Requests are utilized to initiate change or clarify the scope of the contract, allowing the architect to communicate with the contractor about any necessary adjustments to the agreed-upon work. Change Orders formally document any modifications to the original contract, including pricing changes or revisions in scope, ensuring that all parties maintain a clear understanding of the project’s evolving requirements. Certificates of Payment are critical for processing payments to the contractor, outlining the amounts due based on progress and ensuring that work done aligns with contractual terms.

These documents not only keep the project on track but also help to safeguard the interests of all involved parties, ensuring accountability and financial management throughout the construction process. The relevance and necessity of these documents make them essential tools that architects must manage effectively during the contract administration phase.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy