What action is required of the Contractor upon an Owner's convenience termination?

Prepare for the Architect Registration Examination (ARE) 5.0 Construction and Evaluation Test. Study with flashcards and multiple choice questions, complete with hints and explanations. Ace your exam!

When an Owner decides to terminate a contract for convenience, the Contractor is required to cease operations and take protective actions. This means that the Contractor must stop work immediately, ensure that any ongoing tasks are safely concluded, and take necessary steps to secure the site and materials.

This type of termination allows the Owner to end the contract without having to provide a specific reason, and it typically includes the stipulation that the Contractor will be compensated for work completed up to that point, as well as costs incurred from demobilization or other protective measures. The focus here is on minimizing any potential loss and ensuring the project site is left in a safe and secure condition after halting operations.

In this context, other actions like negotiating a new contract, initiating legal proceedings, or revising contract terms are not applicable in the event of a termination for convenience, as the terms of disengagement are already set by the Owner’s decision.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy